Resources · Finance

Stranded capital risk in DER

What happens when a working battery or solar array loses the program, provider or building that paid for it, and the contract terms that keep value moving.

VPP Economics has no affiliation with, sponsorship from, or endorsement by any utility, aggregator, platform, or device maker named here.

The short answer

  • Stranded capital is a working asset with no revenue. The battery or solar array still runs; the program, tariff, provider or building that paid for it is gone.
  • When it happens matters as much as what happens. In our 100 kW battery example, losing all revenue before year 10 leaves the owner below net cost. A program that ends after year 1 still leaves it above net cost.
  • Provider failure is the newest risk. The SunPower and Sunnova bankruptcies left equipment warranties intact but disrupted monitoring, service and guarantees for hundreds of thousands of homes.
  • Contracts decide whether value ends or moves. Assignment rights, buyout schedules, backup servicers and open device standards turn many failures into transfers.

Five ways DER capital gets stranded

Revenue

Program or rate change

A program closes or a tariff is redesigned, and the payment the asset was sized for shrinks or stops.

Counterparty

Provider failure

The installer, lessor or aggregator goes bankrupt or leaves the market, and service, monitoring or dispatch stops.

Technology

Obsolescence

A network, gateway or protocol the device depends on is retired before the hardware wears out.

Site

Building sale or change

The host sells, moves or replaces the roof, and the contract has no clean way to transfer.

Utility side

Stranded grid assets

Pipes and plants retired early are recovered through rates, which changes the bills DER savings are measured against.

Market

Price collapse

Wholesale or capacity prices fall, as PJM’s did to $28.92 per MW-day in 2024/25, and fleet revenue falls with them.

Timing: when the failure happens

Our Finance hub tests four failures at fixed dates. The chart below asks a sharper question: for each failure, how early does it have to happen to push the 100 kW battery below its net cost?

Value kept by failure year

Share of base-case value kept if the failure happens at the end of each year, 100 kW battery, 15 years at 8%.

Swipe to see the full chart →

0%25%50%75%100%yr 0yr 3yr 6yr 9yr 12yr 15Program ends100%Demand charge cut 40%100%Both changes100%All revenue stops100%Net cost line76%Dashed line: net cost after the 30% credit
VPP Economics calculation for the battery on our Hawaiian Electric C&I page: $19,224 a year of demand savings and $6,650 of Fast DR pay. The dashed line is the $168,000 net cost after a 30% credit, 76% of base-case value. Illustrative.

On its own, a program ending pushes the battery below net cost only if it happens before year 1, and a 40% demand-charge cut only before year 2, because the other value stream carries most of the value. Both changes together cross the line if they happen before year 7. Losing all revenue, as with a host sale without an assignment clause or a provider exit with no successor, crosses the line before year 10. A temporary gap is much cheaper: a one-year loss of Fast DR pay in year 6, while a new operator re-enrolls the battery, costs about 2% of value.

The practical lesson: stranding risk is front-loaded. Investors price protection for the first several years far more heavily than the tail, and contract terms such as termination payments are usually set on a declining schedule for the same reason.

Provider failure: two recent cases

SunPower filed for bankruptcy on August 5, 2024, and sold its brand and some assets; the buyer honors warranties only for systems installed by its own companies (SunPower’s warranty page). Several hundred thousand SunPower customers relied on its proprietary gateway for monitoring, and more than 2,500 had switched to Enphase monitoring by April 2025 (Enphase).

Sunnova, the second-largest provider of third-party-owned home solar, filed on June 8, 2025. Its assets were sold and the company wound down; a new servicer took over billing and monitoring (a bankruptcy tracker). Its filings describe how much of the service promise sat with the company: monitoring, performance guarantees and repair warranties attached to its loans, leases and PPAs. Equipment makers said their own product warranties continue.

What survived the bankruptcies

Status of customer protections after two major residential solar bankruptcies.

Swipe to see the full chart →

SunPowerAug 2024, legacy installsSunnovaJun 2025, leases and PPAsEquipment maker’s warrantySurvivedSurvivedInstaller workmanship warrantyLost or at riskDisruptedMonitoring and appDisruptedDisruptedLease or PPA contractSurvivedSurvivedProduction guaranteeLost or at riskDisruptedSurvivedContinued with disruption or a new servicerLost or an unsecured claim
VPP Economics summary. Equipment warranties sit with the manufacturer and survived. SunPower legacy installs lost the company’s bundled labor warranty; Sunnova’s pending guarantee claims became unsecured claims in the case, while the new servicer took over administration. Experiences vary by customer. Sources below.

For an investor the point is structural. Customer protections that depend on the provider’s balance sheet, such as production guarantees, are only as strong as the provider. Pending guarantee claims against Sunnova became unsecured claims in the bankruptcy (OwlWatt’s guide). Protections backed by a manufacturer or a contract that transfers to a successor are much stronger.

Technology obsolescence

A DER asset that earns from a program has to stay connected. When US carriers shut down 3G networks in 2022, starting with AT&T on February 22, solar systems with 3G modems kept producing but stopped reporting, as Enphase warned its customers. Systems that earned solar renewable energy credits from metered production stopped earning them until the modem was replaced. One installer documented a system connected in 2020 that lost monitoring two years later; the replacement modem wasn’t a warranty repair because nothing had failed (Cali Energy’s case study).

For VPP assets, the communications path is the revenue path. Diligence should ask which network, gateway and protocol each device uses, who pays to replace them, and whether the device can be enrolled by another operator using an open standard if the original one leaves.

Stranded assets on the utility side

Utilities face the mirror-image risk, and it flows back into the rates DER is measured against. Massachusetts regulators now require gas utilities to show that non-pipe alternatives such as electrification were considered before recovering new pipeline costs, as the DPU announced with Order 20-80. The follow-up order directs the utilities to forecast how much investment could be stranded and to study accelerated depreciation. The state attorney general’s office defines a stranded asset as one that becomes unnecessary before the end of its nominal service life.

Accelerated recovery of stranded gas assets raises gas bills in the near term, which can improve heat pump economics. Electric-side costs from large-load forecasts that don’t materialize can raise electric rates. Either way, a DER model’s rate path should reflect how the utility recovers its own stranded costs.

Protections that keep value moving

Protection map

Contract terms and design choices against four stranding causes.

Swipe to see the full chart →

Program orrate changeProviderfailureTechnologyobsolescenceSite sale orbuilding changeAssignment clauseLittleLittleLittleStrongBuyout or termination paymentPartialPartialLittleStrongOpen device standardsPartialStrongStrongLittleBackup servicer and step-in rightsLittleStrongPartialLittleMaker-backed warrantiesLittleStrongPartialLittleMultiple revenue streamsStrongPartialLittleLittleShort payback on locked valueStrongStrongStrongStrongStrong protectionPartialLittle or none
VPP Economics summary. “Short payback on locked value” means recovering the cost from locked value and early-year revenue, which shrinks exposure to every cause. Illustrative.
Contract
  • Assignment to a new building owner or host
  • Declining termination payment schedule
  • Purchase option at fair market value
  • Step-in rights for lenders and a named backup servicer
Technology
  • Devices that support open standards such as IEEE 2030.5 or OpenADR
  • Local data access that doesn’t need the provider’s cloud
  • Wi-Fi or wired fallback for cellular links
  • Firmware update rights after a provider exit
Revenue
  • More than one value stream
  • Program terms that match the payback period
  • Revenue reserve or debt service reserve
  • Re-enrollment path in another program
Diligence
  • Provider credit and who backs each guarantee
  • Manufacturer versus installer warranties
  • Site control, roof age and lease terms
  • History of program closures in the territory

Method and caveats

The timing chart uses the 100 kW battery from our Hawaiian Electric C&I page: $19,224 a year of demand savings and $6,650 of Fast DR pay for 15 years at 8%, base-case value $221,468. A failure in year n means revenue through year n, then the changed stream for the rest of the term. Net cost is $240,000 less a 30% credit.

Bankruptcy outcomes summarize public filings, company notices and third-party guides; individual customers’ experiences vary, and the cases continue to develop.